2.11 Checking Out the System
Now that you’ve installed the TracVision G4, you need to verify
that the system functions properly. Check the system startup
routine to ensure that the system is operating within normal
parameters.
To view the startup routine, connect a PC to the ADCU’s
maintenance port. The diagnostics procedure requires Windows
Hyperterminal (or other terminal emulation software, such as
PROCOMM). Use the settings appropriate to your application.
1. Connect one end of the PC data cable to
the DB9 maintenance port connector on the rear of
the ADCU. Connect the other end to the serial port
on the PC (a 9-pin/25-pin connector adapter may
be needed for some PCs).
2. Open the terminal emulation software and
establish the following settings:
9600 baud
no parity
8 data bits
1 start bit
1 stop bit
no flow control
3. Apply power to the TracVision G4 system and
allow the system to complete full initialization.
Data should be scrolling on the PC display to
identify any system problems detected. If no data
is seen, recheck your connections and the terminal
software setup.
A sample startup sequence has
been provided in
Appendix F on
page 143
with the typical ranges
and responses for the
TracVision G4 during startup and
operation.
12 1110987612543 13 14 232221201918 24171615 25 26 353433323130 36292827
48 47 383940414243 3744454660 59 505152535455 49565758
Maintenance
Port (DB9)
Figure 2-39
ADCU Maintenance Port